PROJECT OVERVIEW
Install Head Room equipment to include 1 DC Power Plant, 2 strings of Valve Regulated Batteries, and 36 equipment bays in less than three weeks.

SCOPE
We performed a site survey, conducted a project meeting with the customer, and developed a schedule and resource plan.

Our solution provided:

  • On-site construction and project managers
  • Customer meetings and calls
  • Work schedule and punch list development
  • Field technician scheduling and management
  • Logistics management
  • Delivery of equipment to head end room
  • Removal and disposal of all related trash
  • Equipment installation services
  • All carrier head end equipment
  • GPS antennas
  • RF installation and testing
  • Fiber installation and testing
  • DC power plant AC installation services
  • Materials management
  • All installation materials and management to reduce customer responsibility

Head end room operational to support the NASCAR Race.