Case Studies

Cell Site On Wheels

 

PROJECT OVERVIEW
The COW and Race were in Bristol, TN, while the equipment was located in Charleston, SC.

SCOPE
We de-installed the equipment from an existing COW in Charleston, SC, and installed equipment in the Bristol, TN, COW.

Our solution provided:

  • Project management
  • Work schedule and resource plan development
  • Scheduled and managed field technicians
  • Support for carrier CM’s from two markets 
  • Coordination of on-site work with other subcontractors and trades 
  • Logistics management
  • De-installed equipment retrieval
  • SI fleet (box truck and 4WD trucks) deployment
  • Equipment delivery
  • Equipment de-installation services
  • Equipment installation services
  • Furnished installation materials 

Services completed within 2 weeks to allow System Performance time to test and integrate network.